CONTRACT AWARDS |
|
|
|
|
|
|
|
|
PROJECT NO. |
PROJECT NAME |
DATE OF AWARD |
CONTRACTOR |
AMOUNT |
|
KUCC-0009 |
Renewal and Addition to |
1/4/2007 |
GC - Lobar |
$13,753,000.00 |
|
|
Sharadin Arts Building |
1/4/2007 |
HVAC - Dual Temp |
$5,939,000.00 |
|
|
|
1/4/2007 |
Plbg - Dual Temp |
$1,559,000.00 |
|
|
|
1/9/2007 |
Elec - MBR Construction |
$3,486,000.00 |
|
KUCC-0019 |
Natatorium Repairs |
1/16/2008 |
GC - Uhrig Construction |
$299,700.00 |
|
|
|
1/24/2008 |
HVAC - MBR Construction |
$454,800.00 |
|
|
|
1/17/2008 |
Plbg - Vision Mechanical |
$42,000.00 |
|
|
|
1/18/2008 |
Elec - A.N. Lynch |
$119,410.00 |
|
KUCC-0056 |
North Water Tower Renovations |
12/19/2007 |
GC - U.S. Tank Painting |
$826,100.00 |
|
|
|
1/2/2008 |
HVAC - Blanski |
$85,525.00 |
|
KUCC-0060 |
New Student Housing |
9/5/2006 |
GC - Kinsley Construction |
$27,769,000.00 |
|
|
|
9/19/2006 |
HVAC - H.T. Lyons |
$10,790,000.00 |
|
|
|
9/5/2006 |
Plbg - Jay R. Reynolds |
$7,148,000.00 |
|
|
|
9/5/2006 |
Elec - West Side Hammer |
$6,236,000.00 |
|
KUCC-0062R |
Elevator Modernization |
11/26/2007 |
Elec - H.B. Frazer |
$77,000.00 |
|
|
|
11/21/2007 |
Elev - Reading Elevator |
$222,450.00 |
|
KUCC-0064 |
Deatrick Hall Renovations, |
2/20/2008 |
GC - Cresswell Brothers |
$1,212,977.00 |
|
|
Phase 2 |
2/29/2008 |
HVAC - MBR Construction |
$44,000.00 |
|
|
|
2/26/2008 |
Plbg - Burkholder's Heat & A/C |
$29,600.00 |
|
|
|
2/25/2008 |
Elec - West Side Hammer |
$20,375.00 |
|
KUCC-0065 |
SPF Roofing Restoration |
3/24/2008 |
Hughes Urethane |
$871,000.00 |
|
KUFR-0016 |
Paving Maintenance |
3/25/2008 |
GC - Lehigh Valley Site Cont. |
$475,000.00 |
|
|
Unit price contracts. |
3/20/2008 |
GC - Schuylkill Paving |
$475,000.00 |
|
KUCC-0067.1 |
Facilities Bldg Roof Replacement |
9/12/2008 |
JJD Urethane |
$115,000.00 |
Nondiscrimination and Equal Opportunity are the policies of the
Commonwealth and the State System of Higher Education.
|