INVOICING PROCESS
The
contractor submits invoices in duplicate (all 2 notarized) to the Fiscal
Technician in the Facilities Project Services office. (These need to be
time-stamped due to the 45 days the university has to pay the contractor.)
The date the invoices are to be submitted is determined at the
Pre-Construction Meeting.
GENERAL INVOICE REVIEW
Fiscal
Technician Responsibilities:
G703-Continuation
Sheet for AIA document.
-
Verify
that the Items and amounts match the approved schedule of values.
(These amounts and items are not to change from invoice to invoice.
The only items to be added are any change orders.
Change orders can only be invoiced after the notice to proceed has
been received and the work has been completed.
-
Verify
the amount being invoiced for this period and materials presently stored.
(Columns E and F). The sum of E
& F minus the retainage will equal the invoice amount of G702.
-
Verify
the balance to finish including retainage (Column H plus Column I) equals
line No. 9 on the G702.
-
Verify
the change orders listed on the continuation sheet are fully processed (NTP
issued), amounts on invoice match the approved change order and that each
change order is listed separately. The
total of the change orders on the G703 equal Line No. 2 on the G702.
G702-
Front sheet of AIA
-
Fiscal
Assistant to verify Contract Number, Application Number sequence, Billing
Period and Contract Date.
-
FA
checks the original contract sum is correct along with the change orders to
date. Contract sum to date is
the sum of these two items.
-
Total
Completed & Stored to date should be the same as on the G703.
-
Check
the retainage for the Total Completed & Stored to date (Line No. 5)
-
Check
the Total Earned Less Retainage. (Line 4 less Line 5 total).
-
Verify
previous certificates for payment. (Check previous invoices for amounts)
-
Current
Payment Due equals Line 6 (Total earned Less Retainage) minus Line 7
(Previous Payments).
-
Verify
Balance to Finish, Including Retainage. (Line 3 less Line 6).
This amount should also equal the sum of the totals of Column H and
Column
-
List the amount to be paid (less the retainage) by
purchase order number. The base
contract and each change order will be assigned a purchase order number.
NOTE:
Per ACT 57, the University must pay
the contractor within 45 days of receipt of their invoice.
If any of the above procedures are incorrect, the Fiscal Technician will
notify the contractor via fax and phone and the “clock” stops.
Upon resubmission of the corrected invoice, the “clock” starts again.
The
Fiscal Technician then generates the Invoice checklist and forwards the invoices
with the prevailing wage sheets for additional reviews by the Contract
Specialist, Construction Manager/Project Manager and the Director of Facilities.
The
Contract Specialist Responsibilities:
Review
the submitted certified payroll sheets for:
-
Correct wages are used for the classification
-
Dates on the certified payroll sheets are in line
with the invoice date
-
Approved sub-contractors are
using the prevailing wages determined for the project.
Construction
Manager/Project Manager Review:
Review
the costs and/or stored material submitted for payment.
Paperwork for the stored material must be approved by CM/PM.
Paid invoices of the stored materials must be attached to the current
invoice
-
Review
the schedule of values
-
Review
the retainage
-
Review
the change orders
-
Review
the work completed
-
Review
the prevailing wage to verify the job classifications for work completed
Director
of Facilities/Director of Facilities Project Services Review:
-
Review costs
-
Review
the change orders
-
Review
the work completed
The
invoice is returned to the Fiscal Technician.
One correct original invoice, one set of the prevailing wages sheets and
any additional backup are kept in the FPS files.
The other copies are forwarded to Accounts Payable for payment.